PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PENYELESAIAN PEMBANGUNAN JEMBATAN DENGAN MENGGUNAKAN METODE TCTO (TIME COST TRADE OFF) DAN METODE MANUAL

  • Dayuq Cahyana Universitas Sains Al-Qur’an
  • Agus Juara
  • Wiji Lestarini Universitas Sains Al-Qur'an
Keywords:
penambahan jam kerja lembur, time cost trade off, crash cost, cost slope, metode manual

Abstract

in the implementation of construction projects, actual schedule on the ground which can cause overruns in implementation time and costs, making the project difficult to implement. Causes of delays are changes in project situations, project changes, weather conditions, shortages of manpower, materials or equipment, planning errors or technical data.

Therefore, delays in the implementation of construction projects can be overcome encouraging implementation to achieve goals and plans, one of the acceleration methods available in this way is the TCTO (Time Cost Trade Off) method and the manual method, overtime is around 1 hour and 2 hours. extra hours added. From the analysis that has been carried out, the results obtained for the TCTO method with 1 hour overtime cost reduction of Rp. 259,429,883.74, 2 hour overtime cost reduction of Rp. 237,188,141.75, while the 1 hour manual method reduces costs of Rp. .83,265,953.67, 2 hours overtime cost reduction of Rp.123,410,163.47 from the normal project costs of Rp.15,000,000,000, with a reduction of 1 hour overtime by 10 days, and while 2 hours overtime is 23 days from normal time 150 calendar days.

Downloads

Download data is not yet available.

References

Abimanyuaji P, M. (2021). Analisis Percepatan Waktu Proyek Konstruksi Dengan Metode Time Cost Trade Off (Analysis on Scheduling Acceleration for Construction Project Using Time-Cost Trade-Off Method).
Fadllan. (2017). Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan Kapal: Studi Kasus Pembangunan Kapal Kelas I Kenavigasian Di Galangan Kapal Batam, Kepulauan Riau. Tugas Akhir, ITS.
Frederika, A. (2010). Analisis Percepatan Pelaksanaan Dengan Menambah Jam Kerja Optimum Pada Proyek Konstruksi (Studi Kasus: Proyek Pembangunan Super Villa, Peti Tenget-Badung). Jurnal Ilmiah Teknik Sipil, 14(2), 113–126.
Irawan, Y. A., & Juara, A. (2021). Analisa Optimasi Biaya Dan Waktu Metode Tcto ( Time Cost Trade Off ) ( Study Kasus : Preservasi Jalan Ruas Sp . Gunung Kemala – Sanggi ). 11(2), 16–23.
Nur Aisyah, R. (2018). Pengedalian biaya dan waktu pada proyek penyelesaian gedung perawatan Obsgyn dan anak (Dua Lantai) (Study Kasus : RSUD Kolonedale Kabupaten Morowali Utara). Journal of Chemical Information and Modeling.
Oktaviani, C. Z., Majid, I. A., & Risdiawati, R. (2019). Percepatan Waktu Pelaksanaan Pekerjaan Konstruksi Dengan Metode Cpm Dan Tcto. Inersia, Jurnal Teknik Sipil, 11(1), 33–40. https://doi.org/10.33369/ijts.11.1.33-40
Published
2023-02-09
How to Cite
CahyanaD., JuaraA., & LestariniW. (2023, February 9). PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PENYELESAIAN PEMBANGUNAN JEMBATAN DENGAN MENGGUNAKAN METODE TCTO (TIME COST TRADE OFF) DAN METODE MANUAL. Teras, 12(3), 16-24. Retrieved from https://ojs.unsiq.ac.id/index.php/teras/article/view/4241
Section
Articles

STATISTICS

Abstract viewed = 343 times
PDF (Bahasa Indonesia) downloaded = 0 times PDF (Bahasa Indonesia) downloaded = 148 times

Most read articles by the same author(s)

1 2 > >>